Bishop International Airport

Airside and Landside Expansion

Sorensen Gross provided pre-construction services, construction management and general contracting services for this 78,000 square foot terminal expansion; 50,000 square feet of new construction and 28,800 square feet addition/alteration. Airside expansion included the Golf T Hangers and Storage Tanks. The budgeted amount for this project was $12 million. By reviewing all design drawings prior to release for construction, we were able to make revisions to the layout of facilities and utilities saving the airport $1.8 million. This project was completed three months ahead of schedule. Landside expansion included the addition to the passenger terminal with related demolition, landscaping, signage, boiler and chiller replacement, HVAC and electrical construction. This was a two-story addition to the ticket lobby consisting of 11 ticket counters, 3 offices and bag pick up areas, and 3 takeaway belts. The addition is structural steel with standing seam metal and PVC membrane roofs.

Contract Value » Airside – $10,160,828; Landside – $5,796,927
Project Size » Airside – 50,000 square feet; Landside – 28,800 square foot addition to passenger terminal
Type of Contract » Construction Management; General Contractor
Owner/Location » Bishop International Airport
Jim Rice (Airside) and Mike Trout
(Landside) 810.235.6560
G-3425 W. Bristol Rd., Flint, MI
Architect » Reynolds, Smith & Hills
Dan Clayton and Mike Hopkins
904.256.2338
G-3101 W. Bristol Rd., Ste 300
Flint, MI 48507
Project Manager » Sahar Abdallah
Completed » Airside – August 2000; Landside – December 2004

• Airside Expansion: $1.8 Million Under Budget
• 3 Months Ahead of Schedule